Design and construction of meeting office
Design and Installation of an office for meetings inside the General Assembly hall that ensures thermal and acoustic insulation.
Complete design and execution of the camera - 3D measurements
Design and construction of architecture and installations (power supply, lighting, crane 3.2, complete HVAC system, fast doors, emergency lighting)
New constructions
Small buildings, metal structures, aluminum carpentry, PVC carpentry, drums, etc.
Reconditioning and compartmentalization
Interior renovation, plasterboard partitions, epoxy paint for floors, etc.
Design, execution and office partitioning
Quality office design and construction - Magna - 120 minute fire resistance design with own air conditioning and fire detection systems. Partitioning of the main office.
Execution of the concrete platform for logistics - 800 square meters
Design and construction of 800 sqm concrete platform for the logistics department in Heineken Craiova. Installation of a rainwater system with connection to the outlet of the existing system. Installation of traffic protections.
Refurbishment of the cement floor in the warehouse
Epoxy floor application for heavy traffic 800 sqm - Ford Warehouse
Rehabilitation of office and production spaces C19
Design and execution.
Sulfur tank rehabilitation - Heineken
Rehabilitation of a sulfur tank - waste water system - Heineken, by treating concrete and steel reinforcement with Sika solution.
Strengthening the structure with carbon fibers
Consolidation with carbon fibers and accessories, Sika technology, of all support pillars and cracks on the interior floor of the QUALITY building.
Consolidation of the roof structure
Consolidation and reinforcement of the metal structure of the roof, according to Romanian construction standards. Total amount of steel 281 tons.
Consolidation of constructions
Carbon fiber reinforcement, reinforcement of metal structures, etc.
Facades, roofs and skylights
Refurbishment of facades, replacement of asbestos sheets, glass skylights, polycarbonate skylights and window insulation, ventilation grills, etc.
The design and replacement of ventilation grids
The design and replacement of 420 square meters of ventilation grids on the technical floor to make the system work more efficiently on the technical floor of the Dyeing department.
Replacement of roof secured glass
Design, calculation and execution for the solution to heat loss: by lowering the roofs of the hall- Trim & Final Shop by replacing the safety glass with 16 mm polycarbonate 6 / 16-20.
Implementation of fire prevention systems
The design and execution of: sprinklers, flame-retardant and fire-resistant electrical structures, casings and lightning protection systems.
Electromechanical installations
Fire protection systems, sanitary works, heating and installations, gas installations, thermal and acoustic installations, etc.
Metal works
We execute and design metal works such as: the operator’s work platform, stairs and access roads, barriers and railings to secure working spaces, metal structures, crane installations and lifting equipment and tools.
EcoSport Ford Craiova
Design and construction of mechanical parts, electrical installations for the new production line, sprinklers.
Fox Project Ford Craiova
Design and installation of cranes, assembly lines and piston lines.
Install of MAG SPECH 500
Installation, positioning and power supply. Implemented compressed air system and sprinkler installation. Repair of the epoxy floor under the machinery
Implementation of the Einess System
Implementation of the Einess system for checking and identifying engine faults by comparison with a standard image
Installation and commissioning of equipment
Including: delivery, installation in the respective space, mechanical assembly, execution of connections and installation, power supply and electrical connections, commissioning and assistance.
Pipes: Works and Installations
Including design, manufacture and installation: cold and hot water systems, pipe systems, compressed air, fire protection systems, installation and dismantling of pumps, etc.
Assembly and installation of a washing press
Connection to utilities, execution of a concrete perimeter wall, installation of electrical and automation systems and commissioning of equipment.
Installation of washing filters
Design and execution of FSI washing filters
Office for meetings
Design and Installation of an office for meetings inside the General Assembly hall that ensures thermal and acoustic insulation.
Installation of air diffusers
The supply and installation of 167 pieces of air diffusers in the Bodywork section, for the proper heating and ventilation of the production space.
Purchase and Installation of Air Curtains
Purchase and installation of air curtain systems 36KW / piece - in the Magna logistics area. Automatic systems were installed for the two fast access doors.
Air management systems
Air conditioning, ventilation and extraction, air pressurization, etc.
Industrial cooling systems
Cooling cabin parts
Modification of the body cooling system
Increasing the suction capacity by changing the piping routes and increasing the capacity of the fans.
Installation of temperature controllers
20 temperature controllers were purchased and installed in the Paint Mixing Room - Paintshop and implemented in the existing PLC system.
Replacing the PLC in the Paint Mixing Room
Replacing the PLC - the paint control system for the paint booths - Paint Mixing Room Realization, implementation of the automation program.